Questions? +1 (202) 335-3939 Login
Trusted News Since 1995
A service for gold trading professionals · Friday, February 21, 2025 · 787,886,317 Articles · 3+ Million Readers

Solidus Resources, LLC Announces Positive Feasibility Study Results for Its Spring Valley Gold Project in Nevada

/EIN News/ -- RENO, Nev., Feb. 18, 2025 (GLOBE NEWSWIRE) -- Solidus Resources, LLC (“Solidus” or the “Company”) is pleased to announce the results of the Spring Valley Gold Project (“Spring Valley” or the "Project") Feasibility Study prepared by lead consultant Ausenco Engineering Canada ULC (“Ausenco”) with an effective date of January 31, 2025. The Project is located in Pershing County, Nevada.

This news release contains forward-looking information about expected future events and financial and operating performance of the Project. Risks and assumptions set out in Forward Looking Statements located on page 7 of this release. All dollar amounts are expressed in U.S. dollars, unless otherwise noted.

Project Highlights

  • Large-Scale, Low-Cost Gold Production
    • 10-year plus life of mine averaging over 300 koz gold per year (excludes residual leach year), with 348 koz gold per year over the first five years
    • Life-of-mine (LOM) all-in sustaining costs (AISC) of ~$1,103/oz gold
    • Capex intensity of $269/oz Au produced with initial capex of $823M
  • Updated Economics
    • LOM Revenue, EBITDA (excluding state net proceeds tax) and FCF of ~$6.8B, ~$4.1B and ~$2.4B, respectively
    • After-tax NPV5% of $1.5B with an after-tax IRR of 36%
    • Payback period of <2 years
    • Economics are based on consensus gold price of $2,400/oz in 2028E and $2,200/oz LT from 2029E onwards
  • Simple Heap Leach Operation
    • Single, large open-pit mine design with a straightforward layout
    • Ore is highly amenable to heap leaching with minimal deleterious elements
    • LOM strip ratio of 2.9 : 1
  • Mineral Resources
    • Mineral Resources of 4.4 Moz gold of Indicated resources (inclusive of Reserves) and 0.6 Moz gold of Inferred resources calculated using a gold price of $1,700/oz and cut-off grade 0.004 oz/ton
  • Strong Exploration Upside
    • Resource expansion and exploration targets located nearby and along strike in a 30,396 acres land package

Since consolidating 100% of Spring Valley in 2015, Solidus has substantially de-risked the Project through multiple campaigns including drilling, metallurgical testwork, hydrological tests, and geotechnical analyses, increasing the total drilling at the Project to over 950,000 feet. The Project is on-track to receive all permits in 2025 for construction and operations.

Solidus anticipates that construction of Spring Valley will be led by the mine building team from Waterton Mining, which is nearing completion on the 50,000 ton per day Mineral Park Cu-Mo mill restart (Arizona) and is tracking on-time and on-budget for processing ore in H1 2025.

Chairman Commentary

Isser Elishis, Chairman and CEO of Waterton Mining (100% owner of Solidus) commented, "The Spring Valley Project will be Nevada’s next large heap leach gold mine with a 10+ year mine life and first quartile AISC. The completion of the Feasibility Study represents another major milestone in the advancement of the Project towards a construction decision in H2 2025. The Project is expected to create 1,000+ direct and indirect jobs in the local community. The Feasibility Study reflects market pricing and real-time capital and operating costs applying experience from Waterton’s recent Mineral Park construction project. We anticipate leveraging the expertise gained from Mineral Park and presence of over a decade in Nevada towards the construction and operation of Spring Valley upon receipt of full permits, anticipated in Q2 of this year.”

Feasibility Highlights

  • Large, heap leach gold project with Mineral Reserves of 3.8 Moz gold in the Tier-1 mining jurisdiction of Nevada
  • 10-year active mine life followed by 9 months of residual leaching
  • Ore treated through one of two processing streams that includes higher-grade crushed and lower-grade-as-blasted run-of-mine (ROM) ore
  • Conventional heap leaching and an Adsorption Desorption Recovery (ADR) circuit and refinery that will produce doré onsite

Summary Economic Metrics

Area Item Unit Total
Mine

Ore tons Mined Mton 243
Gold Grade oz/ton Au 0.016
Gold Contained Moz Au 3.8
Strip Ratio Ore : Waste 2.9
Average gold recovery % 80.5
Average gold production in first 5 years koz pa 348
Average gold production LOM# koz pa 303
Capital Cost
Initial Capital $M 823
Peak Investment $M 820
Total Investment $M 1,282
Costs
NSR $/ton ore 28.00
Site Costs $/ton ore 9.79
Royalties % of NSR 4.3
All In-Sustaining Costs $/oz Au 1,103
Financials
EBITDA $/ton ore 17.00
EBITDA Margin EBITDA / NSR, % 61
Annual FCF $M 297
Total EBITDA $M 4,131
LOM NCF $M 2,381
Post-Tax NPV5% $M 1,520
Cash Flow Index NPV : Peak Investment 1.85x
IRR % 36.1
Simple Payback year 1.8

Notes:

  • Excludes residual leach year.
  • Economics are based on consensus gold price of $2,400/oz in 2028E and $2,200/oz LT from 2029E onwards.
  • Includes closure expenses and salvage value. EBITDA = earnings before interest, taxes (excludes state net proceeds tax), depreciation and amortization; NSR = net smelter return; NPV = net present value; IRR = internal rate of return.
  • Post-tax NPV5% / Peak Investment.

Mine Plan

The mine plan will entail excavation of 957 million tons of material mined during ten years while process operations are active. Following the completion of pit operations, process operations will continue for a further 9 months of residual leaching.

Spring Valley is expected to be mined from a single open pit utilizing 320-ton autonomous haul trucks and hydraulic face shovel excavators. Blasthole drills will also use autonomous drill system technology.

The Project contains 3.8 Moz Au of proven and probable mineral reserves at an average gold grade of 0.016 oz/ton.

Spring Valley Annual Gold Production

Spring Valley Annual Gold Production


Spring Valley Mineral Reserve Estimate (Effective Date: September 3, 2024)

Classification

Tonnage Gold Grade Contained Metal
(‘000 tons) (oz/ton) (koz Au)
Proven -- -- --
Probable 242,977 0.016 3,799
Total 242,977 0.016 3,799

Notes:

  • The Mineral Reserve estimate was prepared in accordance with the 2014 CIM Definition Standards by Dave Penswick, P.Eng. an independent mining consultant.
  • The Mineral Reserve estimate is contained within pit designs using Indicated Mineral Resources only and a gold price of $1800/oz.
  • The Mineral Reserve estimate is based on an ore cut-off grade of 0.004 oz/ton gold.
  • Excludes contained gold in overliner material.
  • ROM design ore recovery: 79% of oxide contained; 70% of transition contained; 56% of sulfide contained. Crushed design ore recovery: 88% of oxide contained; 80% of transition contained; 74% of sulfide contained.
  • Mining costs: Average base mining cost: $1.53/ton Ore; $1.36/ton Waste Rock; $0.98/ton Alluvium; mining cost adjustment factor: $0.048/ton per 25 ft bench.
  • Process costs: $2.65/ton ROM ore; $3.23/ton crushed ore; refining costs: $0.75/oz; general and administrative (G&A) costs: $0.80/ton total ore; transport costs $0.63/oz gold.
  • The Mineral Reserve estimate is reported within a pit design that uses geotechnical parameters developed by WSP, where the recommended pit slope angles range from 34 to 47 degrees.
  • Unplanned dilution averaging 14.3% was estimated and included in the reserves.
  • There are no known legal political, or environmental risks that could materially affect the potential development of the Mineral Reserve estimate.
  • Royalties were applied to the Spring Valley Mineral Reserves with an average royalty burden of 4.3% of net smelter return (NSR). The individual effective royalties are between 1% and 6% as described in the Feasibility Study.

Processing

Gold recovery values are based on extensive metallurgical test work, trade-off studies and optimization.

Ore is expected to be treated through one of two process streams that include (1) higher-grade ore crushed in three stages and stacked on the crushed ore pad with conveyors, and (2) lower-grade material will be delivered by open pit haul trucks to the ROM ore pad.

Key Process Design Criteria

Description Unit Crushed Ore ROM Ore
LOM Ore Reserve Mton 123.4 119.6
Ore Throughput Mton per annum 12.8 4.5 - 20.0
Stacking Method - Crushing & Stacking ROM Truck Dump
Gold Head Grade, LOM avg oz/ton 0.025 0.006
Average Gold Recovery % 82.0 74.2


Capital Expenditure

The Project’s initial capital cost is $823 million expressed in Q3 2024 dollars. This estimate falls under AACE Class 3 Classification Guidelines, with an expected accuracy of ±15% of the final Project cost including contingency.

Sustaining capital is estimated to be $388 million. Reclamation capital and bond interest total $87 million ($84 million after discounting), and salvage value applied at the end of the LOM is $13 million. This results in a total LOM investment of $1,282 million.

Capital Cost Summary

Description Initial Capex
($M)
Sustaining Capex
($M)
Total Capex
($M)
Mine Development 275.1 287.6 562.7
Site Preparation 143.4 6.8 150.2
Process Facilities 155.9 7.8 163.7
Heap Leach 81.8 73.5 155.3
Sub-Total Direct Costs 656.2 375.7 1,031.9
Indirect 86.9 5.3 92.2
Provisions (Contingency) 79.6 7.3 86.8
Sub-Total Indirect Costs 166.5 12.6 179.0
Project Total 822.7 388.3 1,211.0

Note: exclusive of reclamation, salvage and reclamation bond interest.


Operating Costs

Operating costs over the LOM were estimated at $2.4 billion, equivalent to $9.79/ton processed, and include mining, processing and G&A costs. The operating cost estimates are reflective of Q4 2024 pricing and don’t include allowances for inflation. The cost estimates align with the principles of a Class 3 Feasibility study level estimate with a ± 15% accuracy according to the AACE guidelines.

LOM Operating Cost Summary

Cost Area $/ton Processed Total ($M) Percent of Total (%)
Mining 6.10 1,482 62.3
Process 2.88 701 29.5
G&A 0.80 195 8.2
Total 9.79 2,378 100.0

Notes:

  1. Ore Processed includes 123.4 Mtons Crush Leach and 119.6 Mtons ROM Leach.
  2. Ore Processed excludes 5.8 Mtons sub-grade material used as liner that contribute 4koz payable Au.
  3. Excludes TCRC costs which are equivalent to an additional $0.02/ton ore.

Mineral Resource Estimate and Exploration

The Mineral Resources at the Project total 4.4 Moz gold of Indicated resources and 0.6 Moz gold of Inferred resources constrained within a $1,700/oz gold pit shell and cut-off gold grade of 0.004 oz/ton. During operations, RC grade control in advance of blasthole drilling will be carried out to assist with medium-term planning.

Spring Valley Mineral Resource Estimate (Effective Date: August 24, 2023)

Classification

Tonnage Gold Grade Contained Metal
(‘000 tons) (oz/ton) (koz Au)
Measured -- -- --
Indicated 259,802 0.017 4,362
Total M&I 259,802 0.017 4,362
Inferred 44,354 0.014 618

Notes:

  • ton=short tons, oz/ton=ounces per short ton, koz= kilo troy ounce.
  • The Mineral Resource estimate was completed by Mr. Simeon Robinson, P.Geo., Principal Geologist of AMC.
  • There is no known depletion by mining within the model area.
  • Near surface Mineral Resources are constrained by a nominal optimized pit shell.
    • Metal prices of $1,700/oz Au.
    • Pit angles vary from 32° in alluvium to 43°.
    • Crusher process recoveries of 88.7%, 87.4%, and 74.9% for oxide, transitional, and sulfide respectively, and ROM process recoveries of 80.1%, 71.10%, and 62.5% for oxide, transitional, and sulfide respectively.
    • Mining costs $1.43/ton autonomous, processing costs $2.90/ton (ROM), $4.40/ton (crusher), G&A costs of $0.79/ton, selling costs of $1.42/oz.
  • The individual effective royalties are between 1% and 6% as described in the Feasibility Study.
  • Cut-off grade applied to the pit constrained Mineral Resources is 0.004 oz/ton (~0.137 ppm) Au.
  • Drilling results up to February 3, 2023.
  • Rounding of some figures may lead to minor discrepancies in totals.
  • Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
  • Indicated Mineral Resources are inclusive of Mineral Reserves.
  • CIM Definition Standards (2014) were used for reporting.


There is strong potential for defining additional Mineral Resources outside the current resource pit, including extensions to the Spring Valley Deposit, multiple exploration targets nearby, and targets along a 7-mile strike length across the Black Ridge fault zone. The Project is located in the Humboldt Range that has a gold endowment of ~60 Moz within a ~50-mile radius.

Spring Valley Property and Nearby Au-Rich Deposits

Spring Valley Property and Nearby Au-Rich Deposits


About Solidus Resources, LLC

Solidus Resources, LLC is a gold developer focused on advancing the Spring Valley Gold Project in Pershing County, Nevada, through permitting, construction and into operations. Solidus is a wholly-owned subsidiary of Waterton Mining, a private equity backed mining company.

For further information, please visit the Solidus Resources website at www.solidus-resources.com.

Alternatively, please contact:

Jack McMahon, President

info@solidus-resources.com

Feasibility Study Report and Contributing Authors

The Feasibility Study for the Spring Valley Project was led by Ausenco Engineering Canada ULC with additional contributors to the report including Lincoln Metallurgical Inc, AMC Mining Consultants (Canada) Ltd, NewFields Mining Design & Technical Services LLC, Ray Walton Consulting Inc, Sunstone Environmental Solutions LLC, Gibsonian Inc, WSP USA Inc, and FloSolutions USA Ltd.

As Solidus is a private entity not soliciting capital and not a Reporting Issuer under either Canadian or US securities law, the disclosure requirements of NI 43-101 and SK-1300 do not apply.

The Feasibility Study supporting the results disclosed herein will be published on Solidus’ website within 45 days. The effective date of the Feasibility Study report is January 31, 2025. For readers to fully understand the information in this release they should read the report in its entirety when it is available on Solidus’ website, including all qualifications, assumptions, exclusions and risks. The technical report is intended to be read as a whole and sections should not be read or relied upon out of context.

Forward Looking Statements

Certain information contained or incorporated by reference in this release constitute forward-looking statements, including, without limitation, any information relating to strategies, plans, future financial or operating performance (including costs or recoveries) and other similar guidance. Forward-looking statements generally can be identified by the use of forward-looking terminology such as “may,” “should,” “could,” “would,” “predicts,” “potential,” “continue,” “expects,” “anticipates,” “future,” “intends,” “plans,” “believes,” “estimates” or similar expressions or their negatives, as well as statements in future tense. Although Solidus believes that the expectations reflected in such forward-looking statements are based upon reasonable assumptions, beliefs and expectations, such forward-looking statements are not predictions of future events or guarantees of future performance, and actual results could differ materially from those set forth in the forward-looking statements. Some factors that might cause such a difference include the following: fluctuations in the spot and forward price of gold; the speculative nature of the business of mining; changes in mineral production performance; changes in national and local government legislation, taxation, controls or regulations and/or changes in the administration of laws, policies and practices; timing or receipt of necessary permits and approvals; increased cost and physical risks, including extreme weather events and resources shortages; and increased costs associated with mining inputs and labor. Any forward-looking information presented herein is made only as of the date of this release, and Solidus does not undertake any obligation to update or revise any forward-looking information to reflect changes in assumptions, the occurrence of unanticipated events, or otherwise.

Photos accompanying this announcement are available at:

https://www.globenewswire.com/NewsRoom/AttachmentNg/32cb0a21-b596-46ae-9fc5-cbfe9816d4df

https://www.globenewswire.com/NewsRoom/AttachmentNg/da814940-32bf-4d1f-ac81-962573e518a1


Primary Logo

Spring Valley Annual Gold Production

Spring Valley Annual Gold Production
Spring Valley Property and Nearby Au-Rich Deposits

Spring Valley Property and Nearby Au-Rich Deposits
Powered by EIN News

Distribution channels: Banking, Finance & Investment Industry, Mining Industry ...

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Submit your press release